Formula and worked example
For identical rectangular excavations, let L and W be reference horizontal length and width, D be uniform vertical depth, c be optional horizontal working clearance on each side, and n be the excavation count. Effective dimensions are L + 2c and W + 2c. Bank volume B = (L + 2c)(W + 2c)D × n. When clearance is disabled, c = 0. The added clearance volume equals B minus LWD × n; the expanded footprint counts the corners once.
Bank volume describes material before disturbance, in its in-place state. Loose volume after excavation = B × (1 + s/100), where s is your bank-to-loose swell percentage. The difference is B × s/100. Swell changes the material volume after excavation, not the size of the excavation envelope. A 20% entry is factor 1.20; it is not a compacted-fill percentage.
Independent US example
A 20 × 12 ft excavation with uniform 4 ft depth and no added clearance gives 960 ft³ bank volume. Divide by 27 to obtain 35.555555556 bank yd³ (BCY), or 27.184172728320 m³. At an illustrative 20% swell, loose material is 1,152 ft³, or 42.666666667 loose yd³ (LCY), or 32.621007273984 m³. The 192 ft³ swell increase does not increase the bank excavation quantity.
Enabling 2 ft clearance on every side changes the footprint to 24 × 16 ft. Bank volume becomes 1,536 ft³ and the clearance adds 576 ft³. At 20% swell, loose volume becomes 1,843.2 ft³, or 68.266666667 yd³. Two identical non-overlapping excavations give 3,072 ft³ bank and 3,686.4 ft³ loose; the dimensions of each excavation stay unchanged. If your original dimensions already are 24 × 16 ft, keep clearance disabled to avoid adding it twice.
Independent metric example
A 5 × 3 m rectangle at 2 m vertical depth gives 30 m³ bank and 36 m³ loose at 20% swell. A 0.5 m clearance at each side gives a 6 × 4 m footprint and 48 m³ bank per excavation. Three identical excavations total 144 m³ bank. The swell increase is 28.8 m³, giving 172.8 m³ loose material. The 20% input is an arithmetic example, not a soil classification or recommended allowance.
Enter the intended excavation extents
Use plan dimensions and a uniform depth from the survey or excavation layout. If the reference dimensions are a structure or work zone that needs a uniform extra working envelope, enable clearance and supply that distance. Clearance expands length and width, never depth. The model is a rectangular prism of unchanged width with depth; it does not infer side slopes, benches, shoring or a support arrangement.
The count repeats identical, separate excavations. Overlapping envelopes must not be counted twice. Split stepped or changing-depth work into appropriate non-overlapping quantities outside this one-box model. It does not automatically deduct existing structures, empty voids or material retained within the envelope. Irregular terrain, battered sides and varying sections need a takeoff matching that geometry.
Keep bank, loose and compacted quantities separate
Bank cubic yards and loose cubic yards are both volume units, but describe different material states. Changing swell leaves bank volume unchanged. Zero swell makes loose and bank volumes equal; 100% swell doubles the loose volume. Use project measurements or geotechnical/material data for the percentage. This page does not infer material factors from a soil name, predict settlement, compute compacted fill/backfill, select truck loads, estimate weight or price excavation work.
One international foot is 0.3048 m exactly; 1 ft³ = 0.028316846592 m³, and 1 yd³ = 27 ft³ = 0.764554857984 m³. The existing Cubic Yard Calculator remains a general volume tool. This excavation page labels the in-place envelope and separate excavated loose material explicitly.
Input and display limits
Length, width and depth accept ft, in, yd, m, cm or mm, independently, and up to 18 decimal places. Positive dimensions must be 0.000001–1,000,000 ft; expanded plan dimensions also may not exceed 1,000,000 ft. Enabled working clearance accepts 0–100 ft per side; hidden clearance is ignored when disabled. Count must be a whole number from 1 to 10,000. Combined bank volume is limited to 1,000,000 m³. Swell accepts 0–100% with four decimal places. These are calculation safeguards, not excavation-design limits.
Decimal dimensions, exact conversions, clearance geometry, repeated quantities and swell arithmetic use exact fractions. Results display to three decimals, without rounding up to an order increment or truckload. The separate loose-volume reporting figure rounds up to the next 0.1 m³, retaining exact multiples; this does not change the bank or loose calculation. Very small valid quantities may display as zero at this precision. Geometry here does not establish an excavation method or support design; take those requirements from the project layout and design.
Primary references
Caterpillar: Swell & Void Percentage, Load Factors describes swell as an increase from the original bank state to the loose state. Caterpillar: Material Density Tables to Help Estimate Earthwork Volumes distinguishes bank, loose and compacted states. References inspected 30 October 2026. Civilable uses the stated bank-to-loose percentage formula and original examples; it does not select material-table factors or apply a compacted-volume adjustment.