Formula and worked example
Start with the fill envelope at the intended finished grade. For a rectangle, horizontal area A = length × width. For a measured plan area, use that area directly. With uniform finished depth D, finished fill V = A × D. A separate optional ratio F is defined here as loose delivery volume divided by finished fill volume; loose delivery = V × F. This definition is specific: do not enter a bank-to-loose swell factor unless it also represents the required loose-to-finished relationship.
Example: a 20 ft × 12 ft area raised by 2 ft requires 480 ft³ at finished grade, or 17.778 yd³. Using an illustrative 1.25 loose-to-finished ratio gives 600 ft³ or 22.222 loose yd³. The extra 120 ft³ is the volume difference between material states, not an additional increase in finished grade. The retained volume is 480/600 = 80%.
A volume ratio is not a density specification
A ratio of 1.25 means 1.25 loose units for every 1 finished unit. It represents 20% reduction from loose volume, not 25%: 1 − 1/1.25 = 0.20. If a verified material loses 25% of its loose volume, the corresponding ratio is 1/(1 − 0.25), about 1.3333, rather than 1.25. Volume retention is not a specified percentage of laboratory maximum dry density. No Proctor target, moisture requirement, lift thickness or bearing suitability is calculated.
Metric and known-area examples
A 10 m × 8 m footprint with 0.3 m finished depth needs 24 m³ at grade. A stated ratio of 1.2 gives 28.8 m³ loose delivery. For 0.25 international acre at 6 in depth, horizontal coverage is 10,890 ft² and finished fill is 5,445 ft³ = 201.667 yd³. A 1.25 ratio gives 6,806.25 ft³ = 252.083 loose yd³. Coverage entry modes are alternatives, not quantities to add.
Measure the fill you actually need
Use horizontal plan area and the difference to the intended finished grade. Uniform depth assumes level, parallel reference surfaces. For variable depths, slopes or irregular terrain, obtain a surveyed takeoff or calculate separate non-overlapping zones with verified depths. The tool does not deduct existing pipes or footings, compute cut/fill balance, add sloped edges, remove topsoil or design an embankment. It does not establish that a material is clean, suitable or structurally acceptable.
Assumptions and limits
The default 1.25 ratio is an editable example, not a universal fill-dirt allowance. Obtain a matching ratio from project material data or your supplier/project team. Turn loose delivery off when no suitable ratio is available; the result then reports finished volume only. Active dimensions must be 0.000001–1,000,000 ft after conversion; known area is 0.000000000001–1,000,000,000,000 ft². Finished volume is capped at 1,000,000 m³ and optional ratios at 1–5 with four decimal places. These are software bounds. Exact decimal fractions are used before three-decimal display rounding. No delivery-load or supplier-order rounding is applied.
References
FHWA earthwork design guidance distinguishes excavation, loose transport and compacted fill states and the need for material adjustments. NIST SP 811 conversion factors supports US/metric unit conversions. The formula and examples above are geometric calculations; neither reference establishes a project-specific delivery ratio. Sources checked 4 November 2026.
Related tools
Use the Topsoil Calculator for planting-layer coverage and its allowance options. For removed in-place material, use the Excavation Calculator or Trench Excavation Calculator. Finished fill is not automatically equal to bank excavation.